The industrial and business park is also quipped with a full array of utilities and amenities. Clean water and steady power run amply and smoothly inside Clark, with standby power generator. Telecommunications and data transfer facilities are also state of the art. The park is situated at the heart of a fiber optic loop that connects Clark to other major Philippine cities and to the world Internet backbone.
In addition, high quality housing at reasonable cost and proximity to leisure and tourism estates, recreation areas, sports and entertainment centers create a highly livable environment for both employees and expatriate staff.
The current facilities include much of the world-class infrastructure left behind by the departing military forces, supplemented by new and upgraded communications and basic utilities. These include a high capacity fiber optic communication and data transfer system, a newly constructed power plant assuring reliable power supply, and water sewerage systems operated by French multinational Vivendi.
Power Distribution
- Residential and General Service Rates
- Residential
First 100 KWH P0.85/KWHExcess KWH P0.80/KWHMinimum Charge: P10.20 for the first 12 KWH
Power Factor Adjustment (For General Service)
A Power Factor Adjustment (PFA) charge during any billing period shall be added in the power bill if theP.F. is less than 85% lagging. However, for P.F. above 90% up to 95%, a bonus is granted to the customer provided that a P.F. above 95% shall be considered as 95% in the computation of the P.F. adjustment bonus. The P.F. adjustment shall be computed as follows:Charge/Bonus =Total Basic Demand x[ (S.P.F/P.F. ) -1 ] Where S.P.F. =standard power factor, 85%, for penalty and 90% for bonus P.F. =actual power factor The ratio S.P.F./P.F. shall be rounded to four (4) decimal places. - Small General Service
GS-1GS-2GS-3GS-4Connected 2,5002,501 to5,001 to10,000Load in Watts or less5,00010,000 upFirst 5090160350P0.98/KWHNext 150260440900P0.88/KWHNext 3005501,2003,250P0.83/KWHExcess KWH P0.81/KWHMinimum Charge: For Customers NOT using high Momentary Draw machines like transformer-type welders and X-ray equipment, P11.76/month on consumption of12 KWH or less shall apply. Otherwise, P11.76 PLUS an additional charge of P10.00/KVA - Large General Service
For Large General Service customers who guarantee a monthly billing demand of not less than 30 KWH, the following shall apply:
Demand Change: P10.00 per KW of billing demand Energy Change: First 200 hours use of billing demand P0.83/KWHNext 200 hours use of billing demand P0.80/KWHNext 100 hours use of billing demand P0.78/KWHExcess KWH P0.76/KWHMinimum Change: P800.00/month
- Residential
- Industrial Service Rates
- Small Industrial Service (below 40 KWH)
Demand Change: P10.00 per KW of billing demand Energy Change: First 200 hours use of billing demand P0.88/KWHExcess KWH P0.78/KWHMinimum Change: P800.00/month
Power Factor Adjustment (For Industrial Service)
A Power Factor Adjustment (PFA) charge during any billing period shall be added in the power bill if theP.F. is less than 85% lagging. However, for P.F.> above 90% up to 95%, a bonus is granted to the customer provided that a P.F. above 95% shall be considered as 95% in the computation of the P.F. adjustment bonus. The P.F. adjustment shall be computed as follows:
Charge/Bonus =Total Basic Demand x[ (S.P.F/P.F. ) -1 ] Where S.P.F. =standard power factor, 85%, for penalty and 90% for bonus P.F. =actual power factor The ratio S.P.F./P.F. shall be rounded to four (4) decimal places. - Large Industrial Service (40 KWH and over)
Demand Change: P10.00 per KW of billing demand Energy Change: First 200 hours use of billing demand P0.78/KWHNext 200 hours use of billing demand P0.77/KWHNext 100 hours use of billing demand P0.76/KWHExcess KWH P0.75/KWHMinimum Change: P800.00/month
- Small Industrial Service (below 40 KWH)
Telecommunications
|
Installation Charge
|
Monthly Rate
|
|
||
Residential
|
P 2,469.51
|
P 479.51
|
Business
|
P 3,557.02
|
P 822.02
|
(inclusive of one(1) month advance rental and deposit for unit) |
Internet Access | ||||
Type of account | Free Hours |
Start-up Fee
|
Monthly Fee
|
Excess per Minute
|
Plan A | 10 Hours |
P 300.00
|
P 300.00
|
P 1.25
|
Plan B | 20 Hours |
P 600.00
|
P 600.00
|
P 1.00
|
Plan C | 30 Hours |
P 900.00
|
P 900.00
|
P 0.75
|
Plan D | 100 Hours |
P 2,000.00
|
P 2,000.00
|
|
Dedicated Dial-Up | Unlimited |
P 10,000.00
|
P 10,000.00
|
|
Leased Line 64 KBPS |
|
P 55,000.00
|
P 55,000.00
|
|
Leased Line 128 KBPS |
|
P 90,000.00
|
P 90,000.00
|
Water
Note: Hotel and Golf Courses are subject to 15% surcharge on total billing. The standing charges for meters larger than 2i available upon request. Strong effluents (e.g. High Biological Oxygen Demand) may be subject to additional treatment charge to be agreed upon with individual lessee or locator.
Size/Type of Use | Min. Charge | ||||
|
0-10 cu m | 11-20 cu m | 21-30 cu m | 31 cum m up | |
|
|||||
Residential | |||||
1/2" | 15mm |
P 75.00
|
P8.10
|
P8.55
|
P9.00
|
3/4" | 20mm |
P 120.00
|
P8.10
|
P8.55
|
P9.00
|
1" | 25mm |
P 240.00
|
P8.10
|
P8.55
|
P9.00
|
1 1/2" |
40mm |
P 500.00
|
P8.10
|
P8.55
|
P9.00
|
2" | 50mm |
P 1,500.00
|
P8.10
|
P8.55
|
P9.00
|
|
|||||
Industrial/Commercial/Areas | |||||
1/2" | 15mm |
P 150.00
|
P16.15
|
P17.10
|
P18.05
|
3/4" | 20mm |
P 240.00
|
P16.15
|
P17.10
|
P18.05
|
1" | 25mm |
P 480.00
|
P16.15
|
P17.10
|
P18.05
|
1 1/2" |
40mm |
P 1,200.00
|
P16.15
|
P17.10
|
P18.05
|
2" | 50mm |
P 3,000.00
|
P16.15
|
P17.10
|
P18.05
|